V.A.O.T. Historic Bridge Committee
Proceedings
Historic Covered Bridge Committee Notes of August 4, 2003 for:
CILLEY COVERED BRIDGE (#33) IN TUNBRIDGE
Present at Meeting: Committee members Dave Hoyne, Warren Tripp, Eric
Gilbertson, Sue Scribner and Scott Gurley for member Scott Newman. Also in attendance were
Ms. Wendy McCullough from the Town of Tunbridge, Joe Nelson representing the Vermont
Covered Bridge Society, Michael Canavan from The Federal Highway Administration, VTrans
project manager Chris Williams and VTrans project engineer Rob Young.
Project engineer Rob Young provided an overview of the bridge and its current condition in
both written and verbal forms. The ensuing notes are to be read in conjunction with the written
overview provided at the meeting.
- General introduction to the bridge and its history. As stated in the written overview,
the bridge was built in 1883, spans 67 feet over the First Branch of the White River on Russell
Road off VT Route 110 and is a multiple kingpost design. The bridge is currently posted for 3
ton, has a short detour and has limited vertical clearance. The truss capacity has been determined
to be 20,000 lbs and the floor system capacity is 12,000 lbs. The town has no interest in seeing
the carrying capacity increased. The bridge had a new standing seam roof installed last summer as
part of a statewide project. The bridge is currently out of plumb and has guy wires supporting it.
- Roof System - It is the intent to salvage the new roof. Guy wires will be removed,
tie beam will be replaced and damaged knee bracing will be replaced.
- Truss System - Other than a portion of the bottom chord at abutment 1, it is not
proposed that any members will need replacement as there is no visible rot.
- Floor System - It is proposed that all of the existing floor beams be replaced in kind
-- same size as presently there and with the same species of wood (Eastern Hemlock) which
would be treated. It is also proposed that the current 3" Eastern Hemlock plank deck be replaced
in kind -- untreated. There are currently no running boards and none are proposed. Curbing was
suggested inside the structure to both protect the structure and offer some refuge to pedestrians.
The project designers will investigate this further.
- Substructure --Abutment 1 is concrete and presently in good condition. There is
evidence that water is being trapped at the bottom chord. It is proposed that a new concrete
bridge seat and backwall be installed which will raise the elevation a bit to alleviate this situation.
Abutment 2 is laid up stone and there is some evidence of settlement and scour. It is proposed
that it be rechinked as necessary, that the top layer of stone be removed, which does not appear to
be original, which would then be replaced with a new concrete bridge seat and backwall.
- Approaches -- proposed to use weathering-steel w-beam approach rail.
- Siding -- There are currently 2 layers of 3/4" hemlock planking for the siding.
Replacing this with 1" shiplap was discussed. Objections were raised over this as historically it is
not felt that shiplap was used on covered bridges. It is proposed that the current siding be
replaced as is -- with 2 layers put back on as there isn't much overhang on the roof and this will
afford the bridge extra protection from the elements.
Overall, all were pleased with the current condition of the structure and the fact that we are
able to move forward with a project at this time. No objections were raised with the scope of the
project and the work proposed. It was requested that fire retardant and insecticides be
considered. Ms. McCullough did state that the bridge could be closed while the rehabilitation
work is underway; the town does request, however, that all work is completed prior to the start of
the Tunbridge Fair. The project manager will be following up with an informational meeting with
the town in the near future. We do not anticipate meeting again on this project; rather any future
details will be finalized through the Section 106 process.
The efforts by the project engineers to provide comprehensive material for committee review
were acknowledged and very much appreciated.
Respectfully submitted,
Susan Scribner
Chair, Historic Covered Bridge Committee
|