Cooley Bridge Open to Traffic, But . . .
WGN 45-11-07
Pittsford -The plan called for the Cooley Bridge be sided with pine planking, but the
town of Pittsford insisted that the bridge be sided with native hemlock.
The bridge was opened on November 25 without the
siding. The Town removed the detour signs and left the posts in--they will put the signs back up
when the siding is installed. The contractor has signed the change order for the hemlock siding
and is now waiting for delivery.
|
|
Open for traffic, the Cooley Bridge awaits a shipment
of hemlock siding. Photo by Joe Nelson, December 14, 2003
|
Interior view of the newly reopened Cooley Bridge. It can be seen that very little
of the original fabric needed to be replaced. Photo by Joe Nelson, December 14,
2003
|
|
|
An interior view of the upstream side. Note the
sturdy new guard rails protecting the trusses. Photo by Joe Nelson, December 14,
2003
|
An exterior view of the upstream side. The scaffolding remains in place pending
the installation of the new siding. Photo by Joe Nelson, December 14, 2003
|
|