cedar_swamp_pict
Return to Archives
Cedar Swamp Bridge Renovation, a Pictorial, photos by Joe Nelson A Pictorial [WGN VT-01-01] Photos by Eric Foster, April 22, 2008 The water is still too high to any work on the new abutments, so we are working on siding and spraying the bridge with fire proofing and insecticides. The contractor is hopeful to begin abutment work the week of the 28th. We still have considerable work on the abutments and approaches. They still want to be done in June, we'll see if Mother Nature agrees. Eric Foster |