westford2
Back to Front Page.
Bid to Rehabilitate The Browns River Bridge Accepted
Some Fine Timber Carpentry
More Fine Timber Carpentry
An Encore in Timber Carpentry
Roof Work Begins
Abutment Work Starts
Roof-work Moves Rapidly
Abutment Work Underway
The Wing-wall is Poured
The Abutments Nearly Ready
Bridge Nearly Ready To Move
Westford Bridge Back Over River
Westford Bridge Dedicated
BID TO REHABILITATE THE BROWNS RIVER BRIDGE
ACCEPTED
Reported by Phil Pierce
Westford, August 25, 2000 - I think it is official that the Town and Historical Society
have accepted the bid of Renaud Brothers to rehabilitate the bridge and foundations and move it
back on the abutments. It is unclear about the schedule, but will be done by the middle of next
year; maybe much sooner. A synopsis of the work to be done:
The existing timber structure needs
some additional work. The top chord of the south truss has been attacked by Powder Post Beetles
and must be replaced (hopefully no other members will be found to be affected). A few members
must be replaced (one tie beam, a couple of laterals, and a couple of posts). Some missing bottom
kickers between the bottom chord and the posts must be replaced. The large bolster beams
installed earlier must have some additional shear keys installed.
The foundations need to have new
concrete caps and the East Abutment has a bad concrete facing on the downstream side that must
be replaced.
The Town must provide some matching
funds (equivalent work) and the final distribution of who will do what is somewhat up in the air.
The Town will at least do the final site finishing work and may install a timber plank deck.
Return to top
Work Begins Again on Westford's Covered Bridge
Westford, March 29, 2001 - With Renaud Brothers Construction on the job it looks
very much like the old bridge is beginning its final lap on the journey back to its rightful place;
over Browns River where it was built 165 years ago.
The journey began in February, 1987
when Westford residents called a special meeting to save the bridge and the Westford Historical
Society was formed. Fourteen years ago! One can only wonder at the tenacity and dedication with
which Caroline Brown and her team pursued their dream to restore this historic bridge.
Congratulations! Now my fingers are crossed, and they will remain so until the day arrives in the
not too distant future when the bridge sits again on its abutments where it is meant to be.
|
|
Work has sterted on Westford's Browns River Covered
Bridge. Notice the "K" frame brace. The gable end sheathing has been removed to access the
upper chord and bracing.
|
Scaffolding has been installed to facilitate the replacement
of the upper chord. The internal lateral bracing has been tightened with new wedges. The "K"
frame braces will prevent racking during repairs.
|
Return to top
Westford, Wednesday April 18 - This day found the south side of the roof raised and
the upper chord lifted out and placed on saw horses on the ground beside the bridge. Two
modern-day timber framers, Phil Pellerin and John Ferlin, were hard at work duplicating the
joinery used by the builders of the bridge back in 1838.
"We do timber framing down in
southern Vermont," said Pellerin. "We team up with Mike [Renaud] whenever he gets a
bridge."
Pellerin and Ferland had worked with
Renaud on the Hopkins Covered Bridge in Enosburg and on the West Dummerston Covered
Bridge. Both use the Town lattice truss. Westford's bridge uses a multiple-kingpost truss with a
Burr Arch.
Westford's Bridge, also known as the
Browns River Bridge was long thought to be ready to move back over the river after repairs were
made to the abutments. However, when Phil Pierce was hired as project engineer, he found other
problems. See the story "Bid to Rehabilitate The Browns River Bridge Accepted" for details.
The plan is to replace the upstream
upper chord and some other members, repair the abutments, then move the bridge over the river
in July of this year. "Yup," said Pellerin, "We'll put it on two trailers, move it down the road."
|
|
The original chord is laid beside the new timber while John
Ferland (left) and Phil Pellerin transfer measurements and cut the mortises and splices into the
new chord.
|
The new chord will duplicate the original chord which
consisted of three timbers spliced together. Note the "compression" splice in the end of the new
piece. The splice on the original timber has been cut to reveal the rot in the center.
|
|
|
A close-up of the cut away end of the original timber. Holes
drilled by powder-post beetles are evident, some of them indicated by the arrows.
|
In the foreground a new king post is being prepared. The
plywood device perched on the end of the new chord-timber is a pattern used to dimension the
cuts for the joinery. A new tie beam can be seen in the right background.
|
Return to top
Westford, Friday April 27 - A week and one-half has elapsed since the last visit to
the site and the cord sections and timbers that were being crafted on the ground next to the bridge
had been completed and installed into the truss. The plan had been to move the bridge back to the
river in July. The work has been going well enough, it is possible the move may begin in June,
Mike Renaud said. The planned repairs to the abutments, which will be subcontracted, still need
to be done.
|
|
The upper chord is in position above the
kingposts. The tenons at the top of the kingposts can be seen waiting to be set into the prepared
mortises.
|
The mortise in the chord end is ready to
receive the tenon at the top of the end-post. Notice the rafter seats.
|
|
|
A brace is being fitted between a kingpost
and a tie beam. The ends of the tie beam are lapped to seat on top of the chord. All of these joints
are fastened by mortise and tenon. The timber below the tie beam is temporary bracing.
|
The chord is now seated onto the kingpost
tenons and secured with hardwood pegs, also referred to pins, dowels, or treenails. The cluster of
pins in the side of the chord between the leftmost kingposts mark the compression splice joining
the chord-members.
|
|
The roof system is braced high so the upper chord
can be worked on. The crossed members between the tie beams are part of the bridge's lateral
bracing system. |
Return to top
Westford, Monday May 7 - With the upper chord work completed on the east side
and those new kingposts installed, work has begun on the north side. There, the roof has been
lifted to allow the installation of a kingpost and part of the upper chord.
|
|
The roof is raised and a rotted section of the
original chord has been removed. The carpenters are installing a new kingpost.
|
This view of the installation of a new kingpost
shows the lapped lower end of the vertical timber as it is fitted into its recess in the lower chord.
Note the vacant bolt-holes in the arch member and in the lower chord. The carpenter's hand grips
the top of the post next to the tenon that will fit into the mortise in the bottom of the new
chord-section.
|
|
|
The new upper chord section has been readied for
lifting into place. Note the large timber below the lower chord. This is a bolster beam. When the
bridge is on its abutments, the bolster beam is placed on top of the bed timbers and projects
beyond the face of the abutment out over the stream, "bolstering" or reenforcing the parallel
chord trusses, shortening the clear-span.
|
The new upper chord section is fork-lifted
into place.
|
|
The Upper chord and two new kingposts have been
installed on the south side of the bridge. Notice that the braces have been fitted into the seats or
steps cut into the top and bottom of each kingpost. Notice the bottom of the right-most post
extends beyond the bottom of the lower chord. This is called a knob, necessary on a tension
member. The new bolts can be seen at each kingpost station, through the arch-members, lower
chord and bolster beam. A new "kick brace" can be seen at the top of the left-most kingpost. |
Return to top
Westford, Monday May 14 - With the roof system back down onto the top chords,
work on the roof sheathing begins.
|
|
Off with the old: making ready for the new
roofing.
|
Stripped of the shingles, light shows through the purlins.
|
|
|
Stripped to the purlins, the roof is prepared for its
new covering.
|
The destination, the north abutment awaits repairs.
|
Return to top
Westford, Wednesday May 16 - As the carpenters put the finishing touches on the
bridge, work begins on the abutments.
|
|
The roof is prepared for sheathing while
the planking on the portal is renewed. Work continues on the bridge floor system.
|
Work on the north abutment begins with
excavation.
|
|
Back view of the excavated abutment. |
Return to top
Westford, Friday May 18 - Almost there!
|
|
West portal with new sheathing.
|
A good start with the new 24 gauge sheet-steel standing-seam roofing.
|
|
|
7:30 a.m. to 10 a.m.
|
Almost there!
|
|
The roof is finished at 2:30 p.m. |
Westford, Friday June 1 - Abutment Work Underway!
Asked for the date of the BIG MOVE, Caroline Brown replied: "I don't have a date yet, I'll let
you know ASAP. Now with all the wet weather . . . the abutments have to be done, my guess at
this point will be late June or July for the move . . . the concrete has to set a bit."
|
|
Excavating continues around the broken
down-stream wing-wall of the north abutment.
|
A piece of the broken concrete wing-wall
is hauled aside.
|
|
The forms for the new wing-wall footings
are under construction. The south abutment is in good shape. According to contractor Mike
Renaud, all that is needed there is a new cap. |
Return to top
Westford, Wednesday June 6 - Wing-wall Poured! Hallelujah!
As the newly poured concrete begins to set, other preparations for the move of the Browns River
Bridge can begin.
|
|
The wing-wall footing has been cast and the
forms removed. The form for the wing-wall itself is being assembled.
|
The wing-wall forms are assembled and nearly ready for the pour.
|
|
What we have been waiting for: the Big
Pour begins. |
Return to top
Westford, Tuesday June 12 - With the abutments nearly ready the date for the BIG
MOVE is soon to be set!
|
|
The new wing-wall on the north abutment
has been cast and the forms removed.
|
The forms are prepared for casting the new
cap on the south abutment. The north abutment will require a cap as well.
|
Return to top
Joe Nelson, P.O Box 267, Jericho, VT 05465-0267, jcnelson@together.net
Photo copyright © Joseph C. Nelson, Caroline Brown, respectively
This file posted March 30, 2001, revised July 3, 2001, re-coded 03/29/2013
|