Poland Bridge Restoration Progress [WGN
45-08-02].
|
Timbers marked with a red ribbon will be
replaced. Photo by Joe Nelson, Aug. 11, 2003
|
September 22, 2003 - As work on the abutments nears completion repair and
replacement of the floor beams and braces continues. A temporary deck will be laid on the floor
beams for use as a platform to allow work to go forward on the truss and roof system.
Eighteen cracked, broken or rotted king posts and 21
chord-pieces will be replaced, work to begin with the arrival of a timber shipment.
The problem of the "too-short" king post braces will
be solved through the use of shims rather than replacing the braces, which are part of the
historic fabric.
|
|
Newly built south abutment awaits a new cap and
backwall. Photo by Joe Nelson, Sept. 22, 2003
|
Glu-lam floor sections stacked and ready for installation. Photo by Joe
Nelson, Sept. 22, 2003
|
|