poland.030805
Back to First Page.
Poland Bridge Restoration Progress [WGN
45-08-02].
August 5, 2003 - The trusses have been leveled, the racking removed and the camber set
to 18 inches, supported on the steel staging. An 18-inch downstream hook has been removed,
straitening the bridge. The additional bracing installed in the end-panels during the stabilization
phase has been removed.
The bridge has been moved 10 inches back upstream,
restoring its position on the abutments to where it was before the June 15, 2002 high water. The
bridge had been raised an additional three feet above the abutments to accommodate the
installation of the supports used to set the camber. This additional cribbing has been removed and
the bridge now sits at the height above the abutments set at the completion of the stabilization
stage.
Further adjustment to the truss is required, as now
most of kingpost braces appear to be too short to support the current configuration by as much as
four inches. Note also, the lower ends of the bottom kick braces have broken loose from their
fastenings on the tops of the bottom chords--the upper kick braces are dangling from the upper
chords.
|
|
Down-stream side with 18 inches of camber. Photo
by Joe Nelson, August 5, 2003
|
Down-stream side. Detail, lower chord between 1st and 2nd panels.
Photo by Joe Nelson, August 5, 2003
|
|
|
Down-stream side. Detail, lower chord at 2nd and 3rd
panels.
Photo by Joe Nelson, August 5, 2003
|
Down-stream side. Detail, upper chord between 2nd and 3rd panels.
Photo by Joe Nelson, August 5, 2003
|
|
Return to top
© 2003 Joe Nelson, P.O Box 267, Jericho, VT 05465-0267
This file posted August 6, 2003
|