poland.030707
Back to First Page.
Work Continues on Poland Bridge [WGN
45-08-02].
July 7, 2003 - As the rehabilitation of the Poland Bridge continues some questions have
been raised about the disposition of the bridge, according to contractor Alpine Construction's
foreman Jim Ligon
The contractor advises that the bridge was not raised
high enough over the abutments during the stabilization phase performed in the early spring of
2001 and should be raised higher. The south end of the bridge was found to have been shifted
four inches down stream as a result of high water on June 15, 2002 despite the bridge having been
raised three feet higher over the stream.
The contractor also advises that the bridge, when
completed, should not be opened to light traffic as planned, but should be restricted to cycles and
pedestrians;. The proposed three-ton limit can be challenged by many of today's SUVs, Ligon
said.
Work continues toward the objective of overhauling
the trusses and restoring the lost camber. As a first step, the south end of the bridge was leveled
on the abutment, raising the down-stream side approximately three inches.
The work will be done while the bridge remains on
the river supported by steel pilings. No core was taken under the bridge to find bedrock for the
pilings, said Ligon, but a measurement was taken at the railroad bridge down stream and "refusal"
was found to be 25 feet. When that pilings were driven at the Poland Bridge, three lengths, or 140
feet of piling were joined to reach refusal at 102'6" below the river bottom.
|
|
Down-stream side. Three-inch leveling timbers can be
seen.
Photo by Joe Nelson, July 7, 2003
|
Up-stream side. Note strip of concrete exposed when end of bridge moved.
Photo by Joe Nelson, July 7, 2003
|
|
Return to top
© 2003 Joe Nelson, P.O Box 267, Jericho, VT 05465-0267
This file posted July 10, 2003
|