kingsbury update
Return to First Page
Historic Covered Bridge Committee Notes of October 24, 2007 with updates on
February 7, 2008 for:
KINGSBURY COVERED BRIDGE (#40) IN RANDOLPH
Present at Meeting: Committee members Mike Hedges, Warren Tripp, Eric Gilbertson,
Nancy Boone, Bob McCullough, Pam Thurber, Scott Newman and Sue Scribner. Also in
attendance was John Weaver representing the Vermont Covered Bridge Society and Sean
James of Hoyle, Tanner & Associates.
Sean James provided a PowerPoint presentation to supplement a previously distributed
Engineering Study summary report. Following is a very brief summary – more detail
can be found in the engineering report. Please note that since the October 24th meeting,
the Town of Randolph was provided an overview of the report and issues and has
indicated their position on some items. The major item is that the Town requests that the
bridge be rehabilitated to support an H6 loading which has been agreed to by committee
members. Updates are shown in italic print to reflect this.
· Roof System - It is the intent to salvage the existing metal roof. It is assumed that
approximately 8 rafters will need replacement and 1 will need repair. The roof
boards appear to be in good shape with no action necessary. It is recommended that
wood blocking be installed between the support beam and the top chord of the
trusses at 16 locations adjacent to each kingpost for which there in no crossbeam. It
is also recommended that additional ‘X’ bracing be added along the top chord
between existing crossbeams.
· Truss System - Approximately 2 member of the north king post need replacement
as well as 4 truss diagonals which have split ends to support the current H4 loading.
As an H6 live load capacity will be accommodated, more replacement or
strengthening– approximately 8 additional diagonal members - will be needed. It is
estimated that approximately 10% of the chord members will need replacing. Some
other repairs such as with epoxy and through bolts may be necessary. Some minor
amount of siding may need replacement as well as the siding on the portals.
· Floor System - complete replacement of the decking with 3” x 8” planks is
recommended. As the bridge will be rehabilitated for an H6 capacity, all the
existing 4 “ x 10” floorbeams will be replaced with new Douglas fir 4” x 12 ¾ “
floorbeams. In addition, a new wood curb is recommended.
· Substructure – Abutments are in good shape. Some repairs will be needed to the
abutment stems and all 4 wingwalls. Remaining cracks should be sealed; graffiti
removed and weep holes installed.
· Approaches – It is recommended that some paving of the approaches occur as well
as installation of weathering steel guardrail.
· General – There is a dry hydrant located at the southeast corner. It is proposed that
fire retardant and insecticide be applied. As well, a Protectowire system is
recommended by the consultant but the Town has indicated they don’t want this.
· General Discussion – It was suggested that the Town be asked whether or not
snowmobiles use the bridge; if so, runners may be warranted. Also, will curbing
hinder the farmer who regularly uses the bridge? In that there is a very low traffic
count and it doesn’t appear that there is a need for the bridge to carry heavy vehicles
(there aren’t any homes on the other side of the bridge), there appears to be an
opportunity to perform minimal repairs with no structural changes due to loading and
traffic. In many cases changes are needed to meet current traffic needs, so this
appears to be a good opportunity to minimize change and work. Nancy questioned
paving the approaches – others agreed that it would alter the setting and is not
desired. Also, does the curbing need to be treated? Opposition to the use of
weathering steel guardrail was voiced. Some like it, other don’t. Can we use steel-backed timber guardrail – not sure there is room for the posts. Could steel posts be
used? Could decking be of oak? It will last longer. 4” x 8” decking was suggested.
It was agreed that an oak deck would be used with no runners. Also, no paving of the
approaches. Non-treated curbing would be installed. Approach rail is needed but the
type is still undecided.
Respectfully submitted,
Susan Scribner
Chair, Historic Covered Bridge Committee
Return to top
Joe Nelson, P.O Box 267, Jericho, VT 05465-0267
This file posted 02/09/2008
|