Hutchins Bridge Reconstruction Progress - August 13
WGN 45-06-07

Work on the Hutchins Bridge truss's is mostly complete except for the upper chords, which await a shipment of "trunnels." The abutment facewalls have been cast and cured while the forms and re-bar for the back and wingwalls are being readied at both portals.

Hutchin's Bridge. Photo by Joe Nelson
August 13, 2009
Hutchins Bridge East Portal.
The Jewett Brothers signature end-posts are shown here. The post on the left has been replaced due to extensive rot. The original fabric of the post on the right has been kept, the rotted lower half replaced by splicing. The end posts at the west end of the trusses have been repaired in a like manner.
Photos by Joe Nelson, August 13, 2009
Hutchin's Bridge. Photo by Joe Nelson
August 13, 2009
Abutment and lower chord repair detail at east portal.
Hutchin's Bridge. Photo by Joe Nelson
August 13, 2009
Completion of repairs to rotted upper chords on the upstream truss wait for a shipment of trunnels.
Hutchin's Bridge. Photo by Joe Nelson
August 13, 2009
A view of another section of rotted upper chords on the south truss.
Hutchin's Bridge. Photo by Joe Nelson
August 13, 2009
A view of the upper chords at the west end of the upstream truss.
Hutchin's Bridge. Photo by Joe Nelson
August 13, 2009
West portal view showing the forms for back and wing-walls under construction.