Delhi, NY - Fitches Bridge Restoration Nears Completion.
Thursday, Nov. 1, 2001 - Hi Everyone! I thought you might enjoy seeing some new
photos on the progress made on the Fitches Covered Bridge - NY-13-02. These were taken on
October 28th.
Doesn't it look fantastic? As you will see, windows
were added, as in the Hamden Covered Bridge, to allow for kids to fish and hopefully less
destruction to the bridge.
Trish Kane
Delhi, NY - Fitches Bridge Restoration Underway.
Sunday, 10 Jun 2001 - Hi Joe - thought it was time for a brief update on Fitch's
Bridge.
I have attached three photos that offer a representation of
our status. The first depicts the removal of the corners of the existing abutments to accommodate
the slightly longer trusses when rebuilt (recall that we are restoring the trusses to their original
length and eliminating the significant weakness introduced by their shortening in the way it was
done).
The second photo shows a fascinating home chewed out of
a pair of top chord members in a way such we did not know it existed until we removed the
outside stick to replace an inside stick for other reasons. We're not sure just what critter made
this home, but it was extensive and effectively removed the entire pair of chord sticks from any
assistance with supporting axial compression in the bridge. The redundant nature of the Town
Lattice bridge was a saving grace to enable the bridge to remain standing.
The third photo shows the flared arrangement of the
bottom chords when the bridge was moved to this site and the results of some pretty bad rot. The
flaring will be replaced with conventional parallel lattice members to the end of the rehabilitated
structure. Note also that the older work caused the truss to be supported by both upper and
lower bottom chords over a short length.
We have identified the lattice members that have to be replaced due primarily to deterioration
in the lower bottom chord connections (I have just taken a bunch of photos of these conditions
and will forward on later). Due to the surprise with the critter home in the top chord, we will
separate all of the top chord pairs looking for other surprises.
We have the first and large load of
timber on hand, but have had to order twice more for the new surprises. We will be focusing on
repair of the upstream truss first in its entirety while we await delivery of the remaining timbers
which will allow us to finish both trusses.
Due to major powder post beetle
damage in the trunnels, we have ordered replacements for all of them. We are using glue-lam floor
beams that should be delivered shortly. Slow going what with all of the other project interruptions
ongoing around the County. We are still on target for completion by the fall.
As always, I'm here to respond to
queries - I would much prefer to answer questions, rather than have questions go unanswered or
be the subject of speculation. Thanks, Phil Pierce
Monday, 11 Jun 2001 - Joe - three more photos to add to the last.
This photo of the abutment work is a better overall shot of
work at one end of the bridge with the two corners formed for new concrete.
This close-up of a section of bottom chord lattice shows
some of the deterioration we found behind the chords. This was obviously hidden from view at
first. It also clearly depicts the problems with lattice connections at times - these holes can't do
their job.
This side view from Route18 provides a view of the trusses
supported by the falsework with work platforms in place. The trusses are nearly stripped of all
bad material, with the exception of some of the lattice members that are still in place.
As of today, the guys installed the first new members in the old truss. The rebuilding is now
underway. Phil