Creamery Bridge Reconstruction Progress - June 3
WGN 45-06-09


creamery Bridge. Photo by Joe Nelson
June 3, 2009
South Portal View - June 3, 2009
The bridge roofing, siding, and superstructure is complete. Abutment and approach work remains to be done.
creamery Bridge. Photo by Joe Nelson
June 3, 2009
View of the bridge from the north, or Hill West Road end, June 3.
creamery Bridge. Photo by Joe Nelson
June 3, 2009
This lower chord-end configuration is found nowhere else among Vermont's covered bridges.
creamery Bridge. Photo by Joe Nelson
June 3, 2009
The abutments are in fair to poor condition. The northeast stone wing has failed completely, requiring reconstruction. The south abutment requires extensive areas of new stone masonry wing construction and existing stone masonry re-pointing. Also, portions of the stone abutment backwall require rebuilding and the west abutment itself requires new bolster beam seats.