comstock.030915
Back to First Page.
Comstock Bridge Reconstruction Progress
WGN 45-06-04.
September 15, 2003 -
The construction and assembly of the Comstock Bridge roof system is well underway as is the new nail-lam floor.
New ridge-pole section being fashioned from native spruce.
Photo by Joe Nelson, Sept. 15, 2003
Broken-out Knee-brace mortise in end-post is repaired with epoxy
Photo by Joe Nelson, Sept. 15, 2003
Installing new nail-lam floor.
Photo by Joe Nelson, Sept. 15, 2003
Roof system nears completion.
Photo by Joe Nelson, Sept. 15, 2003
Return to top
© 2003 Joe Nelson, P.O Box 267, Jericho, VT 05465-0267
This file posted September 16, 2003