Canyon Bridge Rehab - New Deck Nears
Completion
Jeffersonville, August 23, 2004 - The multi-layered bridge roadway is being
reassembled using the original design. The 8" x 8" floorbeams removed when the bridge was
disassembled have been returned and re-spaced, with six new beams. The existing 6" x 6"
stringers were placed on the floorbeams and new 3" x 10" transverse sub-floor planks spaced on
these. New 3" x 8" longitudinal deck planks protected by new 3" x 8" oak running planks
complete the new floor. The distribution beams (or "hanging beams") installed under the bridge in
the 1970s will not be replaced.
|
|
The floorbeams have been laid and spaced. Photo
by Joe Nelson,
August 9, 2004
|
The deck stringers are being laid out atop the floorbeams. Photo by Joe
Nelson, August 16,
2004
|
|
|
The transverse sub-floor planks have been placed and
spaced. The longitudinal deck planks are being lag bolted to the sub-floor. Photo by
Joe Nelson, August 23, 2004
|
One of the three roof beams (tie beams) that needed to be renewed. The roof
system will be reinstalled next.
Photo by Joe Nelson, August 23, 2004
|
|